Chinese Welfare Centre - Belfast

We have recently completed a Grouted DCI job for Mascott on the Ormeau Rd, Belfast. This project was on a tight programme and budget. We enabled the piling to start early on in the contract and other site work to carry on while the piling was underway. This was a small site where the ability to work at different levels and pile into the pre-excavated ground beams and caps saved the contractor a lot of time and effort.

  • 49 Piles were used for the commercial building and for use as a crane base
  • Approximately 12m deep, from pile cut off level
  • Up to 800kn SWL
  • 4 Case Tests
  • 4 CapWaps
  • Vibration monitoring was carried out at all times to a PPV of 5mm/s using our Alarmed Vibration Monitors
  • Static test
  • No spoil
  • No wasted pile cut off generated
  • Main Contractor - Mascott
  • Engineer - White Young Green

 